The most realistic estimate of the time required to complete an activity is referred to as​ what?
a. slack time
b. optimistic time
c. most likely time
d. pessimistic time

Respuesta :

sydneybottom
sydneybottom sydneybottom
  • 11-01-2018
I would say B. optimistic time
Answer Link

Otras preguntas

what mass of NaCl is dissolved in 150 g of water in a .050 msolution?
Could somebody please explain to me how this works?
Part A: Write the meanings of these frequently used idioms. 1. catch a cold 2. see eye to eye 3. under the weather 4. stuffed to the gills 5. out of the frying
A recipe calls for 1/2 lb of flour for 1 batch.How many batches can be made with 3/4 lb.How many could be made with 1/4 lb?
An ore sample weighs 17.50 N in air. When the sample issuspended by a light cord and totally immersed in water, thetension in the cord is 11.20 N. Find the tota
QUIZ Active TIME REMAINING 57:49 n Fleurette is cor Fleurette is conducting a comparative investigation where she is comparing the average acceleration of two d
Flex gym charges a membership fee of 150.00 plus 40.50 per month to join the gym. A rival gym Able gym,charges a membership fee of 120.00 plus 46.75 per month.
How much money is required to buy 2 cakes of soap at $.18 a cake an 1 dozen eggs at $.65 a dozen
Answer the questions shown in the image below.
What was the goal of trust busting in the early 1900s?