Every network has at least one critical path.
a. True
b. False

Respuesta :

Kalahira
Kalahira Kalahira
  • 24-01-2018
True and it is the longest path of a network diagram. The critical path can be found through the sequence of project activities that add up to the longest overall duration.
Answer Link

Otras preguntas

x+5y=19 3x-6y=-6 consistent or inconsistent and dependent or independent
Why does the effect of rising global temperatures in the ocean have such a broad effect on Earth? a. As water warms, it can hold less carbon dioxide, so more C
what visible evidence indicates that a solution is saturated?
3,153,795,054 in word form
What is the sign of the product? (0.3)(–9.2)(–8.1)(4.2)(–0.8) A. positive B. negative
a bakery has a fixed cost of $119.75 per day plus $2.25 for each pastry. the bakery would like to keep its daily costs at or below $500 per day. what is the max
how many states or parts of states did the us create from the mexican cession ?
what is the answer for this 3/8% as a fraction
what fraction of 1 quart is 3 cups
what function do mosques serve