contestada

In the EST graph above, what is the required time to complete task A? ​

In the EST graph above what is the required time to complete task A class=

Respuesta :

sqdancefan
sqdancefan sqdancefan
  • 06-05-2022

Answer:

  5 time units

Step-by-step explanation:

The number on the arrow in this graph is the task completion time.

__

The completion time for Task A is 5 time units.

Ver imagen sqdancefan
Answer Link

Otras preguntas

Ben, an experienced kayaker, can paddle his kayak at the constant rate of k miles per hour there is no current in the water. When he paddles his kayak against a
In many countries, people are arrested every day for speaking out against their government or its policies. In the United States, people are allowed to speak th
What is responsible for the shift in the job trend, from the use of narrowly defined jobs to the use of broadly defined jobs in organizations?
which expression is equivalent to 7.2 x 7.2 x 7.2 ?
The path of a projectile is
(- 5x³77) ² Can someone Simply this answer
"It is true, we shall be monsters, cut off from all the world; but on that account we shall be more attached to one another."
We will forget this knowledge of what we learned when were older.
"As the unit supervisor, Dionne has begun to allow flexible scheduling for those who want to try it. She is hoping by allowing the flexibility, production will
How do people in Canada adapt to their environment ?