Please answer or i loose grades!!!!!!!!!!!!!!!!

Please answer or i loose grades class=

Respuesta :

sakasaki
sakasaki sakasaki
  • 07-09-2020

Answer:

28

Step-by-step explanation:

To complete the task in 30 days, they need at least 4 people working 7 hours.

( 4 x 7 = 28 hrs/day, 28 hrs/day to complete in 30 days, 28 x 30 = 840 hrs total to complete in 30 days. )

The company decides to have 5 people working 6 hours a day.

( 5 x 6 = 30 hrs/day, ? days to complete, must be 840 hours (30 day time span) to finish.  [tex]\frac{840}{30}[/tex] = 28. )

Answer Link

Otras preguntas

Which expression is equivalent to 6r - 10 + 3r – 2?
What are the points/coordinatesTranslate the object 1 unit left and 3 units up​
Vinegar has a density of 1.05 g/mL. A flask with 76.2 mL of vinegar has a mass of 149.5 g. What is the mass of the flask?
What is the definition of Portfolio? (please help)A) a collection of ideas that describe your skills, writing style, and income B) a collection of materials tha
we have 4 types of teeth what would happen if we have 1 types of teeth
Can some one please help me with is quetion
subtract w from u, then subtract v from the result
Value of the function at x=-3
The area of a rectangular wall of a barn is 56 square feet. Its length is 6 feet longer than twice its width. Find the length and width of the wall of the width
What is f(3)? A. -9 B. 1 C. -1 D . 9