A(n) _____ on a project is a significant event that normally has no duration. a. activity sequence b. milestone c. schedule baseline d. activity attribute

Respuesta :

Vickiee Vickiee
  • 14-03-2020

Answer: b. milestone

Explanation:

A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.

Answer Link

Otras preguntas

Triangle G H J is rotated 90 degrees about point X to form triangle S T R. Triangle GHJ is rotated 90° about point X, resulting in triangle STR. Which congruenc
Name the bacteria found in root nodule of leguminous plants
What is usually true about informative text? A. It provides information about a topic. B. It contains many unfamiliar technical terms. C. It is highly detailed
You have 73 trading cards. Your cousin says that you have 7 less than half the cards he has. You say you have 33 more than one-fourth the cards he has. Can you
Find the length of the short leg on the following right triangle.
what is numrical in math and complex function?[tex] \sqrt{ - i} [/tex]​
Point X is the incenter of ΔABC. Triangle A B C has point X as its incenter. Lines are drawn from the points of the triangle to point X. Lines are drawn from po
Which question is a biased question? (1) How old are you? (2) What is your favorite color out of red, blue, and green? (3) Do you prefer a beautiful sunny day o
6(1+5x)=5(1+6x) solve x
till now, up to now , so far make a sentence​