When a contractor is under a contractual duty to construct a building and the building is destroyed by an act of nature while it is still a work in progress, the destruction __________.

Respuesta :

imustapha180
imustapha180 imustapha180
  • 08-02-2020

Answer: the destruction will not discharge the contractor's duty to perform, but will extend the date of performance

Answer Link

Otras preguntas

Please help I'm having trouble with 2,3,4
If a square has a side length of x + 4 and a perimeter of 44 cm, what is the value of x. *
HELP ME PLS I NEED THIS
Identify what was the impact of political and legal ideas contained in Justinians code
A study was done by an online retail store to determine the rate at which users used its website. A graph of the data that was collected is shown: A line graph
Which barrier limited the spread of the Shang Dynasty to the northwest? pls respod im literally dyig
¿Qué es una casa veraniega? Que es una casa vereniega
Which phrase refers to the collection of geospatial data through the use of satellite images/pictures?
What is Communication?​
What is the difference between external and internal in history?