The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

Respuesta :

dvynnjoku dvynnjoku
  • 07-01-2020

Answer:

The answer is Work Package.

Explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.

Answer Link

Otras preguntas

Which of gypsum’s physical characteristics can be described as nonmetallic? A. cleavage B. fracture C. specific gravity D. luster
−(−2z − 5y) in simplified form.
Choose the problems that are likely caused by urbanization. air pollution declining birth rate forest overgrowth housing shortages overcrowding volcanic erupti
What did french do in the American Revolution War?
I need help filling out this table!
Can someone check my special subject verb agreement worksheet thank you I was really confused. The S or P above the subject is for if it's singular or plural.
What is 11 rounded off to the nearest hundred
True or False. Every paragraph should display unity and coherence.
Which word is not derived from implere? A. comply B. implement C. replete D. satiate
Which sentence is an example of faulty coordination? The debate team has many new members, and the team is not very good yet. Farhad, a member of the debate tea