A project network has the following paths. How much slack does path ABEGHI have?
Path Duration ABDFHI 41 ABEFHI 48 ABEGHI 55 ACGHI 40
a) 0 days
b) 7 days
c) 14 days
d) 17 days

Respuesta :

Otras preguntas

What is 9/10 + 2/100 =
Use order of operations to evaluate the expression below. 11 x 9 + [ 15 - 9 ]
Which of the following is a correctly written book citation?(Jennings 88).(Jennings par. 20).(Jennings "Warfare," 45).(Jennings "Warfare" 45).
Which of these resulted from the First Punic War?Sicily became a Carthaginian province.Rome strengthened its naval force.Roman citizens were allowed to own slav
________summa theologica was used to teach catholic priest
what must be done to breed dogs for a particular trait
Solutions are formed by_____.
Which best describes a material with a low index of refraction (near 1)? A. It causes light to refract significantly. B. The speed of light stays constant. C.
A firework is thrown from the top of a hill. The distance, in feet, between the rock and the ground x seconds after it's set off is given by h(t)=-8^2t + 48t +
Cuando oí que tuviste una fractura en la pierna ______________. A. qué lástima B. lo siento C. me sentí triste D. lo lamento