kaylabee335 kaylabee335
  • 06-03-2024
  • Mathematics
contestada

In a scenario where a and b together can complete a work in 14 days, b and c can complete the same work in 21 days, and c and a can complete the work in 28 days, what is the time taken by a alone to finish the work?

a) 20 days
b) 24 days
c) 30 days
d) 35 days

Respuesta :

Otras preguntas

if u connect 3 resistors, having values 2ohm, 3ohm, 5ohm in parallel, will the value of total resistance of will be 2ohm or greater than 5ohm or lie between 2oh
A small publishing company is planning to publish a new book. The production costs will include the time fixed, costs (such as editing) and variable costs (such
A small publishing company is planning to publish a new book. The production costs will include the time fixed, costs (such as editing) and variable costs (such
cyclone low-pressure storms of high winds that develop over water are called _____
Best Buy sold 638 iPads during the month of May for a total, including tax, of $296,963.48; what was the average cost to the consumer?
solve for y. (24-y)/4=4
what are the factors of 68
solve for y. (24-y)/4=4
a washer and a dryer cost 659$ combined. The washer costs 91$ less than the dryer, how much was the dryer?
six nickels is what percent of one dollar