A can do a piece of work in 14 days and B in 21 days. They begin together, but 3 days before the completion of the work, A leaves off. In how many days is the work complete?
a. 10 days
b. 10 1/5days
c. 15 days
d. 7 days

Respuesta :

Otras preguntas

who was the first president of the united states of america
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
log3(2x-5)=2 Answer is 41/2.  Why?
vesicles that contain a cells digestive enzymes are called ?
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
vesicles that contain a cells digestive enzymes are called ?
who was the first president of the united states of america
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
Alex built a snowman using three snowballs,one small, one medium and one large, with diameters in the ratio 2:3:5.      Although highly unlikely due to the phys
Why are some examples of a chemical reaction not actually foolproof evidence that of a chemical reaction?13, 8th grade, and I'm doing my science lab report: The